06 September 2013, 13:36

The governor of the Bryansk region Nikolay Denin visited pellet plant construction in Suzemsky area of the Bryansk region on 5th of September.

Estonian company Hekotek develops documentation for the pellet production in company DOZ in Suzemsky area of the Bryansk region.
15 000 000 Euros will be invested in new wood pellet plant in the Central Russia. The plant capacity will be 80 000 tons of wood pellets per year Construction in planned to be done in 8 months. Governor of the regions watch over the pellet project.
Most of pellets will be exported to Europe as well as some pellets are planned to be distributed inside the region for domestic consumption. At the same time the number of biofuel boilers is very small in the area. There could be sold not more than 5% of total produced pellets.
This project started to be discussed in 2012 and INFOBIO believes that today everything is arranged and plant construction starts in time.